New Delhi: As of March 2026, a staggering amount of Rs. 92,761 crore has been spent by the National High Speed Rail Corporation Ltd (NHSRCL) on the Ahmedabad-Mumbai high-speed rail corridor (MAHSR), a Right to Information (RTI) application filed by a Deccan Herald reporter has revealed. Per the response, the estimated cost of the ambitious bullet train project is now nearly double of its initial estimate of Rs. 1,08,000 crore, at Rs. 2,02,797 crore.The project, spanning a 508-km corridor passing through Maharashtra, Gujarat and Dadra and Nagar Haveli, has been delayed due to a variety of reasons, significantly bypassing its original completion deadline of 2023. According to the RTI response, the tentative timeline for the project’s completion “can be ascertained after award of all contract packages.”In response to the query on whether a combination of Japanese track technology, non-Japanese signalling and India-built trains was part of the original design, the reply said although the plan was to start the operation using Japanese Shinkansen Rolling Stock, the team has now decided on using an “indigenously developed trainset.”Meanwhile, requests for copies of correspondence between Indian and Japanese officials, especially over reported disagreements on signalling systems procurement, were denied. “The sharing of these documents is restricted as covered under non-disclosure agreement between both the governments,” the response said.It added that the dispatch of the “first indigenous trainset from BEML Ltd” was planned for February next years, with other trainsets being dispatched thereafter.NHSRCL also refused to comment on the Japanese government’s views on the use of India-manufactures trains, saying that such disclosures were prohibited under section (9)(f) of the RTI Act. The mentioned clause exempts authorities from disclosing information received from foreign governments.